Hydroelectric power plant upgrades penstock
Project: Hydroelectric power plant upgrades penstock
Jurisdiction: New Milford, Conn.
Vendors: FirstLight Power Resources, Inc., Blakeslee Arpaia Chapman, Hobas Pipe USA, Kleinschmidt Associates
Cost: $3 million
Date Completed: December 2012
After 47 years, the penstock of New Milford, Conn.'s Rocky River Hydroelectric Power Plant has been replaced, thus ending the cycle of excessive leakage that wasted hundreds of thousands of gallons of water.
The original penstock – a pipe or conduit used to carry water to a water wheel or turbine – was constructed in 1928 of Douglas fir wood and steel rings and was replaced in 1965 with the same materials. As each incarnation aged, it began to sag and leak into the drainage ditches that run parallel to the pipeline, wasting a lot of water that could be conserved for other uses, like turning the turbines at the plant. Plant owner, Richard Laudenat, attempted to slow the amount of water leakage and extend the life of the penstock by installing a second set of bands around its circumference and fit joints around the pipe with wedges. Despite his efforts, the sagging, leaking and aging continued. Kleinschmidt Associates was hired to design a replacement pipeline.
The installation contractor, Blakeslee Arpaia Chapman, took 11 days to remove the existing wood-stave penstock. “We cut the existing penstock into 20-foot sections, and as these sections were removed, we dropped them onto timbers causing them to implode,” Construction Superintendent Joseph DelVecchio, said in a statement.
The $3 million project, funded through capital assets, was initiated in January 2012 and completed in December 2012. The 15-foot diameter wood-stave penstock was replaced with 10-foot diameter fiberglass pipe. Hobas Pipe USA supplied approximately 950 linear feet of 120-inch piping that included three meter joints of centrifugally-cast, fiberglass-reinforced, polymer mortar pipe.
The replacement penstock was designed to be reliable, cost-effective and mostly maintenance free. Most of the replacement penstock was half-buried except for two 20-foot sections at the upper ends of the penstock. These sections, supported on concrete cradles, allows for surface water drainage from a hill above the penstock. Steel transition sections at the upper and lower end of the new penstock allow for the new 10-foot fiberglass pipe to connect into the existing 15-foot steel sections.
After inspection and testing of the new installation, Senior Consulting Engineer for Kleinschmidt, Harold Thompson, says that no leaks have been identified. Laudenat says the new penstock continues to meet all of the company’s expectations, even after its first winter under severe New England weather conditions.
_____________
To get connected and stay up-to-date with similar content from American City & County:
Like us on Facebook
Follow us on Twitter
Watch us on Youtube